Bac Giang strives to open interchange of Hung Vuong overpass to traffic before September 2

Updated: 19:04, 19/08/2022
(BGO) – The construction contractor has currently concentrated man power and machines to construct items under the expanding and upgrading project of the frontage road on the left of national road No.1 from the intersection of national road No.31 to Hung Vuong interchange in Bac Giang city (Bac Giang province) so as to open Hung Vuong overpass to traffic before this September 2.

The provincial Management Board for traffic and agriculture construction investment projects was selected as the project investor and consortium of Hanoi based Thuan An Joint Stock Company and 379 Construction and Investment Joint Stock Company as the contractor of the above mentioned project.

{keywords}

The intersection of Hung Vuong overpass is under construction.

The construction started at February 2022 with major items to expand Hung Vuong overpass up to 4 meters in both side (the bridge is widened up to 22 meters from 16 meters) as well as the road with total execution cost of over 79 billion VND from the provincial budget.

So far, 16 out of 22 spans of the bridge surface have been concreted. Recently, the contractor has arranged enough materials and machine with nearly 100 labours to work overtime at night to complete the remaining items and strive to open the intersection of Hung Vuong overpass to traffic before September 2, three months ahead the set schedule.

To ensure the traffic safety for commuters, Chairman of the provincial People’s Committee ordered the project investor to direct the construction contractor to sufficiently install traffic signs, arrange permanent staff to regulate the traffic and instruct the people in line with the approved programme.

The provincial Public Security Department and municipal People’s Committee were urged to direct competent forces to be on duty and patrol so as to collaborate and guide the traffic vehicles and strictly punish any violator.

Minh Linh
Nhu Nguyet bridge is commenced two months ahead of schedule
(BGO) - Nhu Nguyet bridge is totally invested over 450 billion VND (19.6 million USD). The Management Board for traffic and agriculture investment and construction project (Project Management Board) in Bac Giang province was assigned as the project owner.
Overbridge of Thuong river connected
(BGO) - On May 4, the Management Board of traffic and agriculture construction and investment projects in Bac Giang province held a ceremony to connect the overbridge of Thuong river to link Lien Chung commune (Tan Yen district) and Duong Duc commune (Lang Giang district).
Bac Giang starts construction of A Lu bridge
(BGO) - A Lu bridge in Bac Giang city was commenced on May 31 as one of the components of project to develop urban areas along the corridor of the Greater Mekong Sub-region (GMS), the second phase - component project in Bac Giang province.
Bac Giang association serves as bridge to help disadvantaged children
(BGO) - Bac Giang has thousands of disadvantaged children. With the desire to give the best to children, over the past time, the Association for Protection of Children's Rights in Bac Giang province has connected with organizations and individuals at home and abroad for more resources to help them go to school and make their life less difficult.
Building more bridges to open up connection
(BGO)- In order to expand trade connection and boost investment attraction, Bac Giang province is building series of bridges. The completed projects not only help to remove obstacles and open up more development dimensions but also contribute to creating new faces for the rural areas.