Hanoi’s first metro to operate commercially by year-end

Updated: 07:08, 12/07/2020
The Chinese general contractor for Hanoi’s first metro said the acceptance review of the project is being accelerated to enable commercial operation by year-end.

China Railway Sixth Group Co Ltd, the general contractor of the 13km Cat Linh - Ha Dong metro project, has submitted all requested dossiers for the acceptance review of the project at the request Hanoi Metropolitan Railway Management Board (HRMB), Tang Hong, the Chinese director of the project said.

{keywords}

Trains of the Cat Linh-Ha Dong metro line are ready for a commercial test run, October 28, 2019.

The quality inspection and evaluation of each construction item is well under way, and the HRMB has commented that the acceptance review is being "coordinated well by both parties", he said.

The project’s review is expected to fully complete within July, after which the general contractor will be paid in accordance to the terms of the contract. The project will pilot run for 20 days, during which the State Acceptance Council will be invited to evaluate it.

Once this is done, the Ministry of Transport will take over control of the project, and hand it over to the HRMB, Hong said.

Currently, the 31 experts of the Chinese general contractor have completed their compulsory Covid-19 isolation period, and has started their work on the project. Twelve of these personnel work daily with the HRMB on acceptance procedures, while the rest work on checking the operation of construction items at construction sites, he added.

"The HRMB is speeding up the approval and signature of documents, as well as the most important issue – the payment process," Hong said.

In early June, the Chinese general contractor had asked for $50 million in advance to test run the trains, which was refused by the Ministry of Transport on the grounds that all outstanding costs, which was 78 percent of the contracted amount, had been paid on schedule in accordance with the contract.

In addition to acceptance work, the project also needs to be assessed for technical safety by an independent organization, designated to French firm Apave-Certifer-Tricc (ATC).

However, ATC has begun their assessment a little behind schedule, and has requested some documents that the Chinese contractor cannot currently produce, so Hong has asked that conduction field experiments on some items that lack records take place before the 20 day pilot period.

The Cat Linh-Ha Dong Metro Section runs 13 kilometers from downtown Dong Da District to Yen Nghia in the southwestern Ha Dong District. It is one of eight lines planned in Hanoi.

Construction began in October 2011 and was originally scheduled for completion in 2013. But several hurdles, including loan disbursement issues with China that were only resolved in December 2017, stalled it for years.

Its cost has doubled to VND18 trillion ($776.77 million), with 77 percent of it coming from official development assistance (ODA) loans from China.

Overpass crossing Hanoi – Bac Giang Expressway and national road No 37 opens for traffic
(BGO) – The Head of the Devision of Transport Project Quality Management (Department of Transport) Nguyen Tuan Dung informed that the overpass crossing Hanoi – Bac Giang Expressway and national road No 37 has been completed and put in operation. 
PM inspects progress of Trung Luong-My Thuan Expressway
Prime Minister Nguyen Xuan Phuc on March 8 made a field trip to the Trung Luong-My Thuan Expressway in Phu Nhuan commune, Cai Lay district, the Mekong Delta province of Tien Giang.
Southern expressway to open to traffic in September
A 51-km expressway connecting Can Tho City with Kien Giang Province in the Mekong Delta is scheduled to open in September.
Bac Giang – Lang Son Expressway officially opens to traffic
(BGO) – The Chairman of Lang Son provincial People’s Committee Pham Ngoc Thuong on January 14 inked the Decision No.79/QD-UBND to operate the Bac Giang – Lang Son Expressway from the  Km45+100 to Km109+660 with total length of 64km.
Free toll for Bac Giang – Lang Son expressway on Lunar New Year occasion
(BGO) – The General Director of BOT Bac Giang – Lang Giang Company Vu Minh Hoang on January 5 informed that the People’s Committee in Lang Son province agreed with the investor’s proposal to operate the expressway with free of charge during the occasion of Lunar New Year (Year of the Rat). 

Source: VnExpress