Bich Dong town (Viet Yen) exerts efforts to clear land and attract investment

Updated: 21:17, 27/09/2023
BAC GIANG - HLC Urban and Industrial Construction Development Joint Stock Company (HLC) won the bid to construct Bich Son new residential area project in Bich Dong town on total area of ​​5.4 hectares. About 50 households had agricultural land and graves within the project implementation boundary, which were subject to reclaimed.

In November 2022, Bich Dong Town People's Committee conducted land reclamation and compensation as well as site clearance as regulations. After more than 2 months, about 90 percent of related households received compensation and early handed over the land.

{keywords}

Bich Son new residential area project in Bich Dong town has clear land for investors.

By April 2023, site clearance of the entire Bich Son new residential area was completed with high consensus from whole residents.

In the first 8 months of 2023, Bich Dong town carried out site clearance for 15 projects with a total recovery area of more than 50 hectares. Among these, there were 3 projects with non-budget investment capital, one project has site clearance completed while 98 percent of households received compensation money and handed over the land for the remaining area of 14.8 hectares.

Regarding the new urban area project in Bich Dong town in an area of 30.1 hectares, it was implemented in last July and initially received high consensus from the locals.

According to the Steering Board for Land Clearance in Bich Dong town (Steering Board), sine 2020, the Steering Board has conducted land clearance for 36 projects on a total area of more than 230 hectares with thousands of households involved. Currently, 15 projects have completed site clearance work. The remaining projects basically receive high consensus among the people, many of which have completed 95 percent of the area.

Notably, during the implementation of the above projects, the locality has not had to enforce a single case for land clearance because most of the involved households have received bonuses for early handover of the premises.

Le Hoang Bach, Vice Chairman of Viet Yen District People's Committee affirmed: "As the center of the district, Bich Dong town has the most projects that must be cleared. The land clearance task faces many difficulties due to large area of land for reclamation which are scattered and involve thousands of households. However, thanks to thorough, persistent and flexible leadership in mass mobilization and site clearance, the local authority is trusted and supported by the people. This is a favorable premise to attract investors to the area, contributing to early completion of the criteria for building Viet Yen town, a smart urban area in the future."

Tuan Duong
Land clearance done for expansion project of Nhu Nguyet bridge
(BGO) – As of February 18, 2023, the last in 16 households whose land must be reclaimed to execute the expansion project of Nhu Nguyet bridge (Project) handed over the land for the construction contractor, reported Nguyen Ba Trang, Director of Project Management Board, Commander of Construction Contractor in Bac Ninh province.  
Bac Giang ensures progress of site clearance for industrial parks
(BGO) - This year, Bac Giang province ranks ninth in the country in terms of foreign direct investment (FDI) attraction. In order to lure more FDI, the provincial People's Committee is focusing on directing agencies and localities to speed up the site clearance for newly and expanded industrial parks (IPs) in order to hand over the land to infrastructure investors on schedule.
Measures sought to facilitate customs clearance at Vietnam-China border gates
Deputy Minister of Industry and Trade Tran Quoc Khanh and Executive Vice Chairwoman of People's Government of China’s Guangxi Cai Lixin recently discussed measures to facilitate customs clearance of goods via border gates of the two countries.
Bac Giang focuses on site clearance for Hoa Phu IPs
(BGO) - Vice Chairman of the provincial People's Committee Phan The Tuan on November 17 chaired a conference to review the implementation of infrastructure construction and business projects in the Hoa Phu Industrial Park (IP) and the expanded Hoa Phu Industrial Park - Phase I in Hiep Hoa district.
Bac Giang focuses on land clearance, accelerating construction progress of key projects
(BGO)- Deputy Secretary of the provincial Party Committee and Chairman of the provincial People’s Committee Le Anh Duong on October 18 paid a field trip to inspect the implementation progress of some key projects in the province.