Parliament approves funding for Hanoi's new ring road
The road will stretch 112.8 kilometers, covering 56.5 kilometers in Hanoi, 20.3 kilometers in Hung Yen Province, 21.2 kilometers in Bac Ninh Province, with the rest comprising Hanoi – Ha Long Expressway.
A construction site of Ring Road No.4 connecting Hanoi and northern provinces in 2020. |
It will be carried out in two stages.
Phase one will be built in 2021-2025 and cost VND41.86 trillion of the central budget and more than VND22.47 trillion contributed by Hanoi and both provinces.
Phase two in the 2026-2030 period will cost VND8.79 trillion from the state budget, VND5.71 trillion from locality contributions and more than VND29.44 trillion from a private investor under a public-private partnership model.
As planned, the project will be basically completed in 2026 and open to traffic in 2027.
Hanoi People's Committee will oversee project implementation.
Within two years since the resolution is passed, the NA allows heads of competent agencies to choose contractors for consultation, technical infrastructure relocation, compensation, support and resettlement.