Monday, 14/10/2024
Bắc giang 30 °C / 25 - 30 °C
Hotline: +84.0204.3 856 624

Business
Hot news:
Business
icon
0.5 1.0 1.5
Shares:
icon-zalo

Bac Giang recovers shortcoming, accelerates progress of urban, residential and housing project

Updated: 20:07, 09/03/2023
(BGO) – On March 8, the Vice Chairman of the Bac Giang provincial People’s Committee (PPC) Phan The Tuan chaired a meeting to review the progress to invest and build urban, residential and housing projects without using state budget (Project) in the province.

So far, more than 100 Projects have been executed in the province but most of them are delayed due to obstacles in land clearance.

{keywords}

PPC Vice Chairman Phan The Tuan voices at the meeting.

Concluding the event, the PPC Vice Chairman Phan The Tuan pressed that these above mentioned Projects are key source for budget collection. Particularly, social and worker housing projects receive due attention from the Government, ministries, sectors and PPC in order to meet the people’s housing demand.

With the growth rate and rich potential, Bac Giang has attracted many investors to the real estate. However, the execution of projects using non-budget capital was delayed, leading to the risk of losing huge investors.

The provincial leader stated that some investors or project management board of investors lacked qualification and knowleadge about investment and construction procedure. They relied on consultants and in some case disqualified consultant must be changed, causing extended time.

{keywords}

The social housing project for worker is accelerated in Nenh town (Viet Yen district).

So all Projects must be inspected with specific route for recovery. The Department of Natural Resources and Environment was urged to consult the PPC to issue the policy for settelement, restrict the project adjustment except for special case (to be done with proposal, clear reason, orientation and effective evaluation).

The People’s Committee in the districts and city need to assign the land clearance as the key task for the division, sector and agency while urging regular report of execution result so as to quickly hand over the land for construction. The authority must conduct timely inspection to expedite and clarify the responsibility of parties who fail to fulfil the assigned task.

The investors were ordered to speed up the construction progress on the handed over area with construction permit while selecting qualified consultant to early complete procedure for investment preparation.

Truong Son
Bac Giang to pay housing rent support for labours before August 25
(BGO) – The Pemanent Vice Chairman of Bac Giang provincial People’s Committee Mai Son on August 14 inked urgent correspondence No.3936/UBND-KGVX urging to complete the target of Decision No.08/2022/QD-TTg on March 28 of Prime Minister about implementing housing rent support for labours (Decision 08).
99 percent of labours with approved decision receive housing rent support
(BGO) - Implementing Decision No.08/2022/QD-TTg on March 28 of Prime Minister about implementing housing rent support for labours (Decision 08), so far Bac Giang city and three districts of Viet Yen, Yen Dung and Hiep Hoa have received proposals from 596 turns of businesses to support more than 171,200 turns of labours with total amount of nearly 88 billion VND (3.76 million USD).
Housing rent support timely removes difficulties, ensures progress
(BGO) – The northern province of Bac Giang is one of localities gaining positive result in disbursing expenses for labour housing rent support in line with Prime Minister’s Decision No.08 on March 28 2022. However, all sectors and levels have focused on various implementation solutions to ensure the progress of document reception before the deadline of August 15, 2022 to timely pay for labours.
More than 57,400 labours benefit from housing rent support
(BGO) - Implementing Decision No.08/2022/QD-TTg on March 28 of Prime Minister about implementing housing rent support for labours, the People’s Committees in Bac Giang city and three districts of Viet Yen, Yen Dung and Hiep Hoa have received proposals from 293 turns of businesses and supported more than 104,600 turns of labours with total amount of over 52.8 billion VND (2.27 million USD).
Over 73,656 USD paid as housing rent support for Bac Giang labours
(BGO) - Implementing Decision No.08/2022/QD-TTg on March 28 of Prime Minister about implementing housing rent support for labours, the Bac Giang provincial People’s Committee (PPC) has promptly made plan and directed relevant departments, sectors and agencies to communicate and instruct businesses and labours to complete the procedure to receive the assistance.

Shares:
icon-zalo
bac-giang-recovers-shortcoming-accelerates-progress-of-urban-residential-and-housing-project.bbg

Reader's comments (0)

Your comment...