Chairman of provincial People's Committee urges speeding up progress of key projects

Updated: 18:25, 02/04/2021
(BGO) - Chairman of the Bac Giang provincial People's Committee Le Anh Duong on April 1 inspected the construction sites of a number of projects being implemented in Bac Giang city and Viet Yen and Yen Dung districts.

According to the provincial Transport and Agriculture Project Management Unit, for the project to upgrade and expand the frontage road on the left of National Road 1 - section from the National Road 31 intersection to Hung Vuong intersection and renovate Hung Vuong intersection, Bac Giang city’s Land Fund Development Center has basically handed over the site to the construction contractor. Most of the frontage road has been constructed with K95 and K98 foundations, drainage culverts, underground power lines and lighting systems... More than 41 billion VND (1.78 million USD) has been disbursed, reaching over 51 percent of total investment capital.

{keywords}

Chairman of the provincial People’s Committee Le Anh Duong inspects the project to upgrade and expand the frontage road on the left of National Road 1 – section from the National Road 37 intersection to Hung Vuong intersection in Bac Giang city.

However, the progress of site clearance remains slow compared to the plan as there are still some graves yet to be removed. The center is persuading households to relocate graves to hand over the grounds to the construction unit.

The project to upgrade and expand the frontage road on the right of the Hanoi - Bac Giang Expressway – section from the National Road 37 overpass to the National Road 17 overpass, has completed the construction of items as scheduled, disbursing 50 percent of the investment capital. However, at the National Road 37 intersection and a number of frontage road sections in Viet Yen district, there is a need to move electric lines and solve the property of telecommunications businesses and firefighting units. Bac Giang city has not yet cut down trees and unroof temporary houses of some households.

{keywords}

Chairman of the provincial People’s Committee Le Anh Duong directly handles current obstacles at the projects.

The project to build extended Nguyen Thi Minh Khai Road is making foundations and water supply and drainage and electricity systems. The drainage and traffic systems of Zones A and B of the southern urban area of Bac Giang city is also underway. Total disbursement valued at 457 billion VND (19.88 million USD), or over 59 percent of the contract value.

Currently, the construction of the drainage and traffic systems in Zones A and B of the southern urban area of Bac Giang city is about 12 months behind schedule due to difficulties in land clearance. Many households planted perennial trees on agricultural land, some have not received compensation, and others have disagreed with compensation plans or have not determined their exact areas...

After inspecting the construction sites and grasping the specific situations from the investors, the contractors and district and city authorities, Chairman of the provincial People’s Committee Le Anh Duong asked Bac Giang city and Viet Yen district to take drastic measures to accelerate site clearance. They must enhance communications and persuade residents to relocate graves, properties and trees to hand over grounds to construction units, ensuring the progress of the projects. As the rainy season is coming, it is necessary to speed up site clearance for the construction of sewers, ponds and lakes, and have plans for water drainage.

{keywords}

Contractors speed up the construction progress of key projects.

The localities need to consider adjusting a number of locations of the project to upgrade and expand the frontage road on the left of National Road 1 – section from the National Road 31 intersection to Hung Vuong intersection and renovate Hung Vuong intersection to suit reality. For the National Road 37 intersection under the project to upgrade and expand the frontage road on the right of the Hanoi - Bac Giang Expressway - section from the National Road 37 overpass to the National Road 17 overpass, it is necessary to pay attention to creating landscapes and spaces for planting trees, thus creating a highlight and making it the gateway to Viet Yen district.

They should study and have solutions to return internal frontage roads of industrial parks in this area. Regarding the National Road 17 intersection, which involves a number of households, Bac Giang city needs to focus on solving the problems before April 5 to hand over the site to the contractor, striving to complete the project as planned, with ensured quality.

Quoc Phuong

Bac Giang focuses on removing difficulties in site clearance, speeding up progress of key projects
(BGO) - Vice Chairman of the provincial People's Committee Le O Pich on March 23 chaired a meeting to review the implementation of key projects in the province. Attending the event were representatives of some departments, agencies, districts and city, and investors.
Da Nang to outline regional finance center project
Prime Minister Nguyen Xuan Phuc has allowed Da Nang City to draw up a project that would turn it into a regional-level finance center.
Bac Giang commences project to upgrade Yen The Uprising special national relic site
(BGO) – The provincial Department of Culture, Sports and Tourism and the People's Committees of Yen The and Tan Yen districts (Bac Giang province) have jointly held a ceremony to kick off a project to renovate the communal house with three layers of roof in the relic complex of Phon Xuong Post and The Temple in Phon Xuong township (Yen The); and the grand communal house and the rear palace in the Noi communal house cultural-historical relic site in Viet Lap commune (Tan Yen).
Government gives in principle approval to industrial park projects
The Government has given the green light to a number of industrial park projects in the central province of Nghệ An and the northern provinces of Nam Định and Vĩnh Phúc.
Provincial Transport and Agriculture Project Management Unit set up
(BGO) - On the morning of March 1, the provincial People's Committee held a conference to announce decisions on the organizational apparatus and personnel of the provincial Transport and Agriculture Project Management Unit (PMU). Chairman of the provincial People's Committee Le Anh Duong presided over the event, which was also attended by Vice Chairmen of the committee Mai Son and Le O Pich.

Shares:
icon-zalo
chairman-of-provincial-peoples-committee-urges-speeding-up-progress-of-key-projects.bbg

Reader's comments (0)

Your comment...