Efforts made to complete bridge across Thuong River six months ahead of schedule
According to the province’s management board for projects construcing transport and agricultural works, the bridge over the Thuong River, part of a project to build a road connecting National Road 37 - National Road 17 – Viet Yen - Tan Yen - Lang Giang section of Provincial Road 292, has a length of nearly 400 m and a width of 12 m. It is being built by Tan Thinh Construction Co., Ltd at a total cost of more than 122 billion VND (5.34 million USD).
The construction progress of the bridge over the Thuong River is being sped up. |
Thanks to the contractor’s great efforts, the workload has reached more than 60 percent of the plan.
In the coming time, the contractor will continue to mobilize vehicles and human resources to link two parts of the bridge on the occasion of the April 30 Victory anniverary this year. It is expected to experience a technical run on September 2, six months ahead of schedule.