Completing construction of DNP clean water plant in June
The contractors are completing the construction of clean water pipeline passing Song Khe Noi Hoang Industrial Park. |
The total work volume achieved 80 percent of the construction items while 20 out of 38 kilometers of water pipeline were installed, ensuring the set schedule. Currently, the contractors have been urged to boost up the construction to put the plant in operation to start supplying the water from June 30 as the plan committed to the provincial People’s Committee.
The plant capacity is designed at nearly 20,000 cu.m per day, ensuring to supply clean water to a part of Lang Giang district, Bac Giang city, Industrial Parks and Clusters in Yen Dung and Viet Yen districts.
The construction of clean water tank has been basically completed. |
The project was commenced in July 2017 in Huong Son commune (Lang Giang district) at a total cost nearly 1.5 trillion VND (65.8 million USD). The plant provides the water from Cam Son lake in Luc Ngan district treated by a modern process to the local resident and enterprises to meet the rising demand
Van Thuong
Reader's comments (0)