Nhu Nguyet bridge to complete on May 19
The Project received total investment of over 450 billion VND (over 19.1 million USD) by the Bac Giang provincial Management Board for Agriculture and Traffic Investment and Construction Projects.
Workers focus on constructing the remaing item of the bridge deck on Bac Ninh side. |
The project consists of the bridge and frontage roads in both sides with the first end in Quang Chau commune, Viet Yen district (Bac Giang province) and the other in Dap Cau ward, Bac Ninh city (Bac Ninh province).
Workers complete final closing segment for the edge on Bac Ninh side. |
Total length is about 1.32km with Nhu Nguyet bridge stretching over 439m which is built beside the old one by similar structure to serve six lanes.
So far, all leading and casting spans have been completed on Bac Giang side with close segment done for the edge. Meanwhile, all abutments, piers, installations, bridge deck and casting blocks are basically done on Bac Ninh side.
As schedule, the main span of Nhu Nguyet bridge will be closed on May 19, 2023. |
The contractors now mobilize hundreds of labours and machines to accelerate the remaining items to close the main segment of Nhu Nguyet bridge on May 19, 2023.