Bac Giang builds and revamps infrastructure of high value fruit growing area
The routes are constructed in line with the third and fourth level mountainous road standard with total investment of 148.8 billion VND (6.5 million USD) from the budgets of central, province and district.
Illustrative image. |
Luc Ngan district People’s Committee acts as the owner of the project which will be executed from 2021 till 2024. After completion, the traffic routes will assist the development of concentrated fruit cultivation area in Quy Son commune, a part of Phuong Son commune and Chu town.
On September 11, the Standing Board of Luc Ngan district Party Committee had a working session with local competent agencies and authorities in Quy Son and Phuong Son communes to accelerate the site clearance progress for the project which was finalized to be done basically within this September.